Property Code › Title 5 › Chapter 53 › Subchapter J

Texas Property Code § 53.234

Time for Notice

Mechanic's, Contractor's, or Materialman's Lien · Lien on Money Due Public Works Contractor

The lien claimant must give notice not later than the 15th day of the second month following the month in which the labor was performed or the material furnished.

Official text of the Texas Property Code as published by the Texas Legislative Council.

Official source
Legislative history

Acts 1983, 68th Leg., p. 3555, ch. 576, Sec. 1, eff. Jan. 1, 1984. Amended by Acts 1989, 71st Leg., ch. 1138, Sec. 36, eff. Sept. 1, 1989.