Utilities Code › Title 2 › Chapter 39 › Subchapter E

Texas Utilities Code § 39.205

Regulation of Costs Following Freeze Period

Restructuring of Electric Utility Industry · Price Regulation After Competition

At the conclusion of the freeze period, any remaining costs associated with nuclear decommissioning obligations continue to be subject to cost of service rate regulation and shall be included as a nonbypassable charge to retail customers. The commission may adopt rules necessary to ensure that money for decommissioning is prudently collected, managed, and spent for its intended purpose and that money that remains unspent after decommissioning is completed is returned to retail customers.

Official text of the Texas Utilities Code as published by the Texas Legislative Council.

Official source
Legislative history

Added by Acts 1999, 76th Leg., ch. 405, Sec. 39, eff. Sept. 1, 1999.

Acts 2005, 79th Leg., Ch. 121 (S.B. 1464), Sec. 2, eff. September 1, 2005.